Thursday, September 2, 2010

Re: BANYU URIP PROJECT

Dear Ani ,
 
Port Charge At Surabaya .
- OPT Fiost                            :Rp 71.176 / r/t  ( r/t = revenue ton )
- Surcharge 100 %                  :Rp 71.176 / r/t
- Wharfage                             :Rp   1.700 / r/t
- Retribution                           :Rp      150 / r/t
- Receiving mechanic              :Rp 11. 661 / r/t
- Delivery mechanic                 :Rp 11. 661 / r/t 
- Storage at yard                     :Rp   2.000 / r/t / day 
- Houlage                                :Rp 20.000 / r/t
- Wathman ( security )             :Rp 150.000 / day / person  
 
Shore Crane / Houlage .
- Trucking fr ship side to yard    :Rp    350.000 / rit ( normal size 40 ft )
- Trucking sliding                      :Rp 1.500.000 / rit
- Lowbed                                  :Rp 3.000.000 / rit 
 
Shore Crane hire .
- Shore crane 100 T cap            :Rp 1.100.000 / hour with minimum charge 14 hour ( includ mob the mob )
 
Custom Clearance At Surabaya .
- Handling doc break bulk            :Rp    5.000 / M3 / Ton .
- PPJK                                       :Rp 250.000 / document 
- EDI                                          :Rp 200.000 / document
 
Inland Trucking From Surabaya to Cepu .
- Trucking project                        :Rp 3.500.000 / rit 40 feet 
- Trucking project                        :Rp 3.000.000 / rit 20 feet
- Lowbed                                    :Rp 8.500.000 / rit .
 
- The above tariff excluded ppn + pph ..
 
 
Brgds/ Capt Hariyono .           
----- Original Message -----
From: SMS Line
Sent: Wednesday, September 01, 2010 4:07 PM
Subject: BANYU URIP PROJECT

DEAR PAK HARIYONO,
 
LOCATION : CEPU
TOTAL VOLUME : 58,221 CBM GENERAL CARGO
               11,329 CBM HEAVY CARGO
               12,898 CBM ODC
 
PLEASE ADVISE URGENTLY :
- PORT CHARGE (SURABAYA & GRESIK)
- CUSTOMS CLEARANCE ( SURABAYA & GRESIK)
- INLAND TRUCKING (SURABAYA-CEPU & GRESIK-CEPU)
  SIZE 20', 40',OT DLL
 
BEST REGARDS
ANI
 
 